Nebius, a leading neocloud provider, has outlined a capital expenditure plan of approximately $40 billion for fiscal year 2027, a figure that significantly exceeds recent Wall Street projections. Announced during its third-quarter earnings call, the ambitious strategy relies heavily on customer pre-payments and loans secured by contract values to finance the construction of new data center infrastructure. However, the company acknowledged that this financing model carries inherent risks, particularly as ongoing projects face delays and potential cancellations.
CEO Arkady Volozh noted that construction challenges are currently prevalent across the industry, stating that Nebius is not immune to operational disruptions. These warnings come as reports suggest that major clients, including Microsoft, are becoming more cautious about partnerships with neocloud firms that have missed delivery milestones. Microsoft, which is paying for AI computing capacity at a data center in Vineland, New Jersey, is experiencing months-long delays at the site. While Nebius’s contract with Microsoft is valued at up to $19.4 billion, only slightly more than half of the planned capacity is scheduled for delivery by the end of the current year, with the remainder pushed to the second quarter of 2027.
The delays are attributed to the site operator, DataOne, which accelerated the decommissioning of temporary power generators ahead of schedule to transition to Bloom Energy fuel cells. This operational shift has been complicated by regulatory issues; investigative reporting revealed that DataOne operated at least 45 unpermitted natural gas generators at the facility, leading to a $1.1 million fine from New Jersey regulators for violating federal law. Additionally, the facility faces a lawsuit from local residents alleging that the data center emits a persistent humming noise.
Financial analysts note that Microsoft’s contract includes clauses allowing termination if delivery dates are missed without alternative capacity being offered, alongside penalties for late delivery. Although Nebius stated that Microsoft has been involved in the planning process, it has not confirmed whether the client has accepted the revised timelines. Microsoft’s own recent earnings indicated that its capital spending was lower than expected due to third-party delays, prompting the company to tighten oversight of partners such as Nebius, IREN, and Nscale.
Despite the challenges at third-party sites, Nebius maintains that its self-built data centers are operating on schedule or ahead of it. Chief Revenue Officer Marc Boroditsky highlighted that deals with Microsoft and Meta included substantial prepayments received well in advance of delivery. With $7.4 billion in cash held at the end of the quarter, Nebius expects prepayments and asset-backed financing to cover up to 85% of its planned 2027 spending. The company forecasts 2027 revenue between $12 billion and $13 billion, aiming to achieve pre-tax break-even by the fourth quarter.
In its third-quarter results, Nebius reported revenue of $981 million, a 571% year-over-year increase, though the company reduced its 2026 revenue forecast by $200 million to $3 billion, citing the impact of delays at sites like Vineland. The announcement sent Nebius shares down 17% for the day, reflecting investor concern over the scalability and reliability of its neocloud model.
Eighty-five percent financing coverage is high. If delays stretch out, they might run out of runway before delivery.
Self-built sites are on schedule, which is a relief. Hopefully, the Vineland mess gets resolved quickly soon.
Unpermitted gas generators and a lawsuit over humming noise? New Jersey regulators definitely need to step in here.
Prepayment models are risky. If a client walks away due to missed dates, the whole financing structure collapses.
Fifty-seven percent growth is impressive, but cutting the 2026 forecast really shows how messy these third-party delays have been.
Does the break-even target for late 2027 actually account for the potential termination of the Microsoft contract?
That switch to fuel cells causing delays? Plus unpermitted generators? Sounds like a recipe for total disaster, honestly.
The 17% drop in shares says it all. Wall Street hates uncertainty, and Nebius just added a lot of it.
It is bold to commit that much capital when Vineland is already falling behind. Microsoft tightening oversight makes sense now.
Forty billion dollars on prepayments is a massive bet. I wonder if the regulatory fines and delays are going to sour those investors.